NEW QUESTION 91
A company produces pipe at certain fixed lengths.
The company must be able to schedule cutting machines. You set up the cutting machines as resources. All cutting resources can produce many of the products. There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this.
You need to configure the resources to account for these different products.
What should you do?
- A. Create a resource for each length.
- B. Create a resource group for each length.
- C. Build capability related to length and assign to the appropriate resources.
- D. Configure the Data/Hour option on the Capacity unit field on the resource.
Answer: C
Explanation:
Explanation/Reference:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/define-resource- capabilities
NEW QUESTION 92
A company uses separate finished good item numbers for size variations of the same product.
The company wants to minimize the number of variously-sized items that are created.
You need to perform the setup to allow variants in size to the product master.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Answer:
Explanation:
NEW QUESTION 93
You need to create the production orders for standard model bicycles.
Which method should you use?
- A. Master planning execution
- B. Released item
- C. Supply schedule form
- D. Sales order line
- E. All production orders form
Answer: C
Explanation:
Reference:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/supply-schedule
NEW QUESTION 94
A customer produces light projection toys for holiday decorations throughout the year. Vendors have negotiated rebate agreements as a condition of their contact. The contract also contains the visual templates required for the customer to use in a season.
Vendor rebate agreements must only be applied if the following requirements are met:
* Units of measure for deliverables are the same unit of measure as on the agreement
* The agreement is valid as of the date a purchase order is generated
You need to configure the vendor rebate agreements.
What should you do?
- A. Set the Cumulative purchase by field value to the beginning of the season date
- B. Set the Rebate line break type field value to Quantity
- C. Set the Rebate line break type field value to Amount
- D. Set the Unit of measure rebate option field value to Exact match
Answer: D
Explanation:
Section: Create, process, and manage production batch orders
Explanation/Reference:
References:
https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/procurement/vendor-rebates
NEW QUESTION 95
A company uses Dynamics 365 Process manufacturing.
Employees work a half day so that they can attend a company event. You have a rush order that must be completed that same day.
After reviewing the net requirements of the batch order, only 400 of the total quantity of 1400 units must be completed today. The production manager must retain the original batch number as the quantity of 400. The original batch number must appear on documentation for the customer.
You need to split the batch order into two orders.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Answer:
Explanation:
NEW QUESTION 96
You are the production scheduler at a manufacturing company. You schedule estimated production orders and ensure that capacity is used efficiently.
You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.
You need to schedule the order.
Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.
Answer:
Explanation:
Explanation
References:
https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production-control/operation-sch
NEW QUESTION 97
A company that produces rubber hose using Discreet orders accounts for raw material scrap after report as finished though inventory movement journals.
The company has noticed that most of the scrap that is recorded is due to start up that feeds the hose to the finishing process. In addition, the amount of scrap that is recorded is consistent regardless of the amount of hose being produced.
You need to account for material lost during startup.
What should you do?
- A. Do a case study for the scrap items and enter the average amount of scrap as a separate line items on the Bill of materials.
- B. Enter the amount of scrap that is consumed as constant scrap in the Bill of materials.
- C. Enter the consumption amount on the line to match the actual amount used.
- D. Enter the amount of scrap that is consumed as variable scrap in the Bill of materials.
Answer: D
NEW QUESTION 98
You produce 100 total units of finished goods. The amount of material used to produce the goods is the equivalent amount of material needed to produce 105 finished goods.
The company must track variances in material compared to the original estimated amount. You must only use one picking list journal for each production order.
You need to post a picking list that accounts for the material required to produce 105 finished goods.
What should you do?
- A. When creating the lines for a picking list, select the estimated consumption option and override the consumption field with the actual amount to be consumed.
- B. In the Bill of materials production details, edit the estimated amount for each line to equal 105 units of raw material.
- C. Report as finished five additional units into the good quantity and post a picking list for only the originally estimated amount.
- D. Post a picking list for 100 to account for the originally estimated amount. Post an additional picking list to account for the equivalent amount of material to produce 5 finished goods.
Answer: A
NEW QUESTION 99
You work for a gem wholesaler that sells raw diamonds. Diamonds are purchased and sold in individual boxes but weighed and inventoried in carats.
You are setting up a catch weight item for diamonds. Each box of diamonds must be tracked by its individual container weight.
You need to set up this item as a full visibility catch weight item.
Which two steps must you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
- A. Assign a Tracking dimension group with batch number as the only active tracking dimension.
- B. Assign the item a Tracking dimension group with active serial number control.
- C. Create an inter-class unit of measure conversion between boxes and carats.
- D. Assign it a Serial number group with per qty. defined as 1.
Answer: B,C
Explanation:
Section: Create and manage production and lean orders
Explanation/Reference:
References:
https://docs.microsoft.com/en-us/dynamicsax-2012/appuser-itpro/create-a-catch-weight-item-with-full-visibility
NEW QUESTION 100
Note: This question is part of series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company produces and distributes seafood to supermarkets. During the manufacturing process, raw seafood is purchased, cleaned, and packaged into various-sized boxes. Each box may have a different weight.
Product is sold by the box and priced by the pound.
You need to ensure that you can perform transactions at the box level and record the net weight of goods shipped to a customer.
Solution: Set up the product as a catch weight item with batch control. Set the catch weight unit to box and the inventory unit to pounds.
Does the solution meet the goal?
- A. No
- B. Yes
Answer: A
Explanation:
Explanation/Reference:
https://docs.microsoft.com/en-us/dynamicsax-2012/appuser-itpro/about-catch-weight-items
NEW QUESTION 101
You are the product design manager for a computer manufacturer.
Your new laptop model is configurable. There are restrictions on which hardware components can be selected depending on the model. You create configuration groups for hardware and software.
You need to create a new laptop item number and configurations.
In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.
Answer:
Explanation:
Explanation
References:
https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/pim/dimension-based-product-co
NEW QUESTION 102
A company produces lotions for pain relief and uses Dynamics 365 for Finance and Operations.
You have been provided the following information for a new relieving lotion.
Use the drop-down menus to select the answer choice that completes each statement based on the information presented in the graphic.
NOTE: Each correct selection is worth one point.
Answer:
Explanation:
NEW QUESTION 103
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
* Create a vendor resource and work cell for outsourced painting; add the vendor resource to the work cell.
* Create a production flow process activity using the painting work cell and the service item for picking.
* When the service is required, create a purchase order to the subcontracting vendor and add a line for the service item and the vendor price.
Does the solution meet the goal?
- A. Yes
- B. No
Answer: A
Explanation:
Explanation/Reference:
References:
https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production-control/activity- based-subcontracting
NEW QUESTION 104
A manufacturing company uses advanced warehouse management functionality for a new warehouse.
After releasing a production order, you observe that the warehouse work for raw material picking was not generated.
You need to go through the warehouse management setup to determine what is missing.
What three setup configurations must you validate? Each correct answer presents part of the solution.
NOTE; Each correct selection is worth one point.
- A. Wave template.
- B. Work template for raw material picking.
- C. Directive codes.
- D. Confirm the production output location on your resource group.
- E. Location directive for raw material picking.
Answer: A,B,E
NEW QUESTION 105
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solutions, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 Supply Chain Management for their Lean manufacturing environment.
There has been an engineering change to a fixed quantity product that is in production. This change will add an additional processing step as the second step. The existing version must be phased out and replaced by the new version.
You need to ensure that the engineering change takes affect at the end of the month.
Solution:
1.) Create an activity for the new process step and add it to the existing production flow. Set the expiration date to the end of the month
2.) Create a Kanban rule that incorporates the new activity with an effective date of end of the month
3.) Edit the existing Kanban rule. Set the expiration date to the end of the month.
4.) Activate the new production flow
Does the solution meet the goal?
- A. No
- B. Yes
Answer: A
Explanation:
Explanation
NEW QUESTION 106
......
Exam Details and Other Important Features
The Microsoft MB-320 exam comprises of about 40 to 60 questions that need to be answered within 120 minutes. So, it goes without saying that time management will play a key role during this test. The exam questions are mostly based on the multiple-response and multiple-choice formats. The test is available in the English language only. It costs $165. This price applies to the candidates who are located in the United States. For the applicants who are taking the exam in another country, this cost can be different due to local taxation. To learn the actual pricing, visit the official webpage.
Microsoft allows the candidates to cancel the exam 24 hours before the appointment. However, it is important to keep in mind that if one does not show up for the test without canceling or rescheduling his/her appointment, then this means that they will be forfeiting their exam fee. If you are not able to clear Microsoft MB-320 on the first try, there is nothing to worry about because Microsoft allows 5 attempts in a year. So, if you fail the test at your first attempt, you can still have another go after waiting 24 hours. However, if you are still unable to pass it, you will have to wait at least 14 days to take the exam a third time. The waiting period stays the same for the fourth and fifth attempts.
In the Microsoft MB-320 exam, candidates are to discover how Microsoft Dynamics 365 can be utilized in analyzing requirements for a business. They will also be into the translating of the requirements into complete business processes in addition to solutions. This is to ensure the execution of best practices for the industry. Passing it after MB-300 extends the Microsoft Certified: Dynamics 365 Supply Chain Management, Manufacturing Functional Consultant Associate certificate.
Pass Microsoft MB-320 Exam – Experts Are Here To Help You: https://testking.realvce.com/MB-320-VCE-file.html