2024 Realistic RealVCE PMP-CN Dumps PDF - 100% Passing Guarantee [Q365-Q390]

Share

2024 Realistic RealVCE PMP-CN Dumps PDF - 100% Passing Guarantee

Free PMI PMP-CN Exam Questions and Answer

NEW QUESTION # 365
專案經理想要指派一名初級工程師到一個新專案。在過去的專案中,工程師表現出了主動承擔複雜任務並以創新方式解決問題的能力,無需任何鼓勵。然而,工程師拒絕了專案經理加入新專案的邀請。
工程師拒絕參與該專案的最可能原因是什麼?

  • A. 工程師覺得不受歡迎或不喜歡與其他專案團隊成員一起工作
  • B. 專案經理沒有遵循工程師職能經理的正常招募流程
  • C. 專案經理沒有充分支持和認可工程師的職業成長
  • D. 工程師因長時間工作和解決難題而出現“專案倦怠”

Answer: C


NEW QUESTION # 366
專案經理被新分配到正在進行的專案的第二階段。在實施過程中,出現了一個缺陷,而且沒有人知道如何修復它,因為以前的工程團隊已經轉移到另一個專案了。
客戶警告說,此前該缺陷對專案進度產生了負面影響。
專案經理首先該做什麼?

  • A. 更新風險管理計畫。
  • B. 取得知識資源。
  • C. 檢查組織流程資產 (OPA)。
  • D. 延長專案的時間表。

Answer: C

Explanation:
Explanation
According to the PMBOK Guide, 7th edition, organizational process assets (OPAs) are the plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization. OPAs include any artifact, practice, or knowledge from any or all of the organizations involved in the project that can be used to execute or govern the project. OPAs can be grouped into two categories: processes and procedures, and corporate knowledge base. In this question, the project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously, this defect negatively affected the project schedule. The question asks what the project manager should do first.
Based on this information, the best answer is option B, which is to check the organizational process assets (OPAs). This is because checking the OPAs is a project management practice that can help the project manager to find relevant information and guidance on how to fix the defect and prevent further delays.
Checking the OPAs can involve reviewing the processes and procedures, such as the quality management plan, the change management plan, the issue log, the defect repair procedures, and the lessons learned register.
Checking the OPAs can also involve accessing the corporate knowledge base, such as the historical information, the project records, the best practices, and the expert judgment. Checking the OPAs can help the project manager to understand the nature and cause of the defect, as well as to identify and implement the appropriate corrective actions.
Option A, which is to acquire knowledgeable resources, is not a good answer. This is because acquiring knowledgeable resources may not be the first step or the best solution for the project manager. Acquiring knowledgeable resources is a process that involves obtaining the human resources needed to complete the project activities. Acquiring knowledgeable resources may involve hiring, contracting, or training processes.
Acquiring knowledgeable resources may not be the first step, as it may require some prior analysis and planning. Acquiring knowledgeable resources may not be the best solution, as it may involve additional costs, time, and risks.
Option C, which is to update the risk management plan, is not a good answer. This is because updating the risk management plan may not be relevant or effective for the project manager. The risk management plan is a document that describes how risk management activities will be planned, structured, and performed throughout the project. The risk management plan may include the risk management approach, rolesand responsibilities, budget and schedule, risk categories, risk appetite and tolerance, risk identification and analysis methods, risk response strategies, and risk monitoring and reporting mechanisms. Updating the risk management plan may not be relevant, as the defect is not a risk, but an issue that has already occurred and needs to be resolved. Updating the risk management plan may not be effective, as it may not address the root cause or the impact of the defect.
Option D, which is to extend the timeline of the project, is not a good answer. This is because extending the timeline of the project may not be necessary or acceptable for the project manager. Extending the timeline of the project is a process that involves modifying the project schedule to accommodate the changes or delays in the project activities. Extending the timeline of the project may involve submitting a change request to the appropriate authority for review and approval. Extending the timeline of the project may not be necessary, as the project manager may be able to fix the defect and recover the schedule by using the OPAs. Extending the timeline of the project may not be acceptable, as it may affect the stakeholder satisfaction, business value, and project benefits. References: PMBOK Guide, 7th edition; PMP Exam Content Outline; [PMP Sample Test Questions].


NEW QUESTION # 367
項目經理正在領導一個工程項目。項目經理必須在量產前獲得一些認證,計劃在3個月內進行。認證過程至少需要6個月。
項目經理接下來應該做什麼?

  • A. 與高級管理層會面,討論延長項目時間表的可能性。
  • B. 聘請顧問縮短認證流程以滿足進度要求。
  • C. 與項目發起人討論將量產時間延長3個月。
  • D. 評估和評估認證流程並了解最好和最壞的情況。

Answer: D


NEW QUESTION # 368
專案經理委託一家顧問公司進行設計研究,以調查多種替代方案。專案經理對研究成本有嚴格的政策,並建立了許多成本觸發因素和趨勢分析。
專案經理使用哪種工具?

  • A. S曲線分析
  • B. 時間和材料 (T&M) 合約
  • C. 掙值 (EV)
  • D. 控製圖

Answer: B


NEW QUESTION # 369
敏捷團隊在地理上分散在多個大陸,項目經理需要確定管理虛擬團隊之間溝通的工具,將左側相應的工具拖到右側的每個項目任務中

Answer:

Explanation:


NEW QUESTION # 370
在項目實施過程中,一個團隊發現一項關鍵項目可交付成果並未列入預算。項目經理首先應該做什麼?

  • A. 將問題上報給項目發起人以尋求解決。
  • B. 從項目範圍中刪除可交付成果。
  • C. 讓團隊承擔責任並要求立即解決。
  • D. 與團隊會面討論替代方案。

Answer: D

Explanation:
The first thing that the project manager should do is to meet with the team to discuss alternatives. This option allows the project manager to identify the root cause of the problem, evaluate the impact of the deliverable on the project scope, quality, cost and time, and explore possible solutions with the team's input. The project manager can then communicate the issue and the proposed solutions to the project sponsor and other stakeholders for resolution.


NEW QUESTION # 371
專案 A 對公司至關重要,必須在九個月內完成。專案章程已簽署,但專案範圍說明書尚未準備。管理階層要求專案經理在沒有批准的專案範圍說明書的情況下推進專案。
專案經理接下來該做什麼?

  • A. 拒絕參與該項目,因為管理層未遵循標準專案管理實踐
  • B. 使用專案章程中的輸入啟動專案以節省時間
  • C. 將問題回報給專案發起人並加入風險登記冊中
  • D. 與管理階層會面,解釋在沒有專案範圍說明書的情況下執行專案的潛在問題

Answer: D


NEW QUESTION # 372
環境政府機構的監管部門最近禁止生產特定厚度的塑膠包裝產品。該禁令將於
12個月。一家從事替代包裝的新創公司的專案經理一段時間以來一直在關注該法律的進展,並且作為風險管理的一部分,已經確定了可以支持不斷增長的客戶群的新產品。
專案經理接下來該做什麼?

  • A. 組織與所有利害關係人的會議並審查利害關係人參與計劃
  • B. 繼續生產流程並計劃在下一次年度目標審查會議上討論更改
  • C. 12 個月期限結束後開始行銷活動以銷售替代包裝
  • D. 向管理層通報新法律,作為擴大市場份額和分享擬議產品的機會

Answer: D


NEW QUESTION # 373
一名專案經理已被指派負責一個必須在未來幾週內完成的緊急專案。專案經理意識到這將對當地社區產生影響。由於工作地點在學校附近,專案經理與他們進行了接觸以了解他們的需求。
專案經理應如何保證工作順利進行?

  • A. 與學校聯絡,將非工作專案時間納入學校開始和結束時間
  • B. 按計畫繼續工作,並在專案小組到達現場後通知學校
  • C. 建議學校在專案工作期間關閉
  • D. 將專案所需的工作延後到學校假期開始

Answer: A


NEW QUESTION # 374
在一家金融公司,一個策略性專案已計劃使用預測方法。在專案規劃期間,產品負責人要求提交里程碑以供審核。完成專案有明確的範圍和截止日期。
為了滿足產品負責人的期望,專案經理首先該做什麼?

  • A. 通知產品負責人必須等到專案結束。
  • B. 與軟體團隊會面,檢視每月里程碑審核的可能性。
  • C. 修改專案管理計畫以使用敏捷框架來合併里程碑。
  • D. 更改專案章程以表示方法將有所不同。

Answer: B


NEW QUESTION # 375
在上次衝刺評審期間,主要利害關係人抱怨該產品缺少許多他們期待的功能 專案團隊認為每個增量都符合驗收標準並得到了主要利害關係人的批准 專案的成本績效指數 (CPI) 為1 15 且進度績效指數(SPI) 為1.43 專案經理應該做什麼?

  • A. 向利害關係人解釋,由於每個增量的驗收標準都已滿足,因此項目可以關閉。
  • B. 要求專案團隊執行修改,因為專案預算和進度可以支援他們。
  • C. 與雙方分析理解上有差距的原因,協商解決方案。
  • D. 請利害關係人提交變更要求,以增加所要求修改的預算和時間。

Answer: C


NEW QUESTION # 376
專案負責人正在管理執行階段的專案。分配了一位新產品負責人,專案負責人與新產品負責人進行了第一次會議。在會議期間,新產品負責人表示第一個版本的範圍需要更改。
專案負責人應該先要求產品負責人做什麼?

  • A. 建立新的待辦事項清單項目並在下一個衝刺計畫中討論它們。
  • B. 建立新的待辦事項清單項目並在下一個衝刺回顧中討論它們。
  • C. 查看新的待辦事項清單項目並在下一次站立會議中討論它們。
  • D. 檢視版本中包含的現有積壓工作項目的優先順序。

Answer: D


NEW QUESTION # 377
團隊成員正在與專案經理進行討論。在上次回顧會議中,團隊意識到過時的設備可能會影響專案的下一個迭代。團隊建議購買新設備,因為它對於最終交付成果的成功至關重要。
專案經理接下來該做什麼?

  • A. 告訴團隊成員更多設備不屬於專案範圍。
  • B. 檢查專案預算,確認是否有足夠的緊急儲備。
  • C. 提交變更請求以增加預算並購買新設備。
  • D. 審查成本管理計劃以確定如何解決此問題。

Answer: D

Explanation:
Explanation
The cost management plan is a component of the project management plan that describes how the project costs will be planned, estimated, budgeted, managed, and controlled. It also defines the processes, roles, responsibilities, tools, and techniques for cost management, as well as the thresholds, rules, and procedures for handling changes and variances. Therefore, the project manager should review the cost management plan to determine how to address the issue of obsolete equipment that could affect the next iteration of the project.
The cost management plan can help the project manager to identify the available resources, reserves, and funding options, as well as the steps and criteria for submitting and approving a change request, if needed. The other options are not as appropriate or effective as reviewing the cost management plan, as they may not follow the established guidelines or consider the impact of the issue on the project objectives and constraints.
Checking the project budget to verify if there is enough contingency reserve may not be sufficient or accurate, as the contingency reserve may not cover the cost of buying new equipment, or it may be allocated for other risks or uncertainties. Telling the team members that more equipment is not part of the project's scope may not be realistic or feasible, as the obsolete equipment may compromise the quality, functionality, or value of the final deliverable, or it may cause delays, rework, or defects. Submitting a change request to increase the budget and buy new equipment may not be necessary or justified, as there may be other alternatives or solutions to address the issue, or the change request may not meet the approval criteria or process. References:
PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Sixth Edition, Project Management Institute Inc., 2017, pp. 235-236, 247-248, 487.
The ABC of obsolescence management, Netilion Blog, 2023, pp. 1-2.
6 Steps to Equipment Obsolescence Management, Tool Tracking Software, 2023, p. 1.


NEW QUESTION # 378
一家公司正在通過建設新的生產設施來實施增長戰略,該設施很快將進入運營階段。儘管治理政策已經到位,但公司必須遵守最近實施的新財務法規。遵守規定將導致項目範圍發生重大變化。
項目經理應該如何應對這一要求?

  • A. 直接遵守財務法規。
  • B. 繼續執行現有的公司治理政策。
  • C. 進行分析以評估對項目的影響。
  • D. 將問題上報給高層管理人員並讓他們決定。

Answer: C


NEW QUESTION # 379
一家銀行啟動了一個用新系統取代現有核心系統的計畫。該系統將在每個專案交付完成後分幾個階段啟動,這些專案交付必須得到主要利害關係人的批准。
專案經理首先該做什麼?

  • A. 與主要利害關係人就品質標準達成協議。
  • B. 讓經驗豐富的關鍵利害關係人參與專案的實施。
  • C. 開發需求可追溯性矩陣。
  • D. 與主要利害關係人一起檢視測試和檢查計畫。

Answer: A


NEW QUESTION # 380
一家公司的專案管理辦公室 (PMO) 一直在嘗試在專案管理框架中實施自適應方法,並且專案經理被要求在下一個專案中使用自適應工具。這不是第一次提出請求,先前的專案在實施自適應工具時失敗了。
專案經理該做什麼?

  • A. 準備變更請求並尋求指導委員會關於新專案架構的批准
  • B. 向 PMO 建議現在不是開始在專案中實施自適應工具的合適時機
  • C. 與主要利害關係人進行單獨訪談,以了解所有問題,然後製定溝通管理計劃
  • D. 引進第三方公司為此特定專案開發和實施混合框架

Answer: D


NEW QUESTION # 381
去年,一家公司為一個正在進行的專案向外部分承包商支付了 6 萬美元。
專案經理被要求評估今年是否可以透過使用內部勞動力更有效地交付專案。專案經理使用了 4 個月的樂觀期限、6 個月的悲觀期限和 5 個月的最預期期限,並得出結論,可以使用以下資源來交付服務:
- 兩位工程師(每人月薪700美元)
- 專案經理一名(月薪1,600美元)
- 預計每月額外費用 2,000 美元
專案經理使用專案評估和審查技術 (PERT) 來計算專案使用內部資源交付時所節省的成本。
專案經理估計公司可以省多少錢?

  • A. 40,000 美元
  • B. 35,000 美元
  • C. 20,000 美元
  • D. 30,000 美元

Answer: B

Explanation:
PERT formula is (Pessimistic value + Optimistic Value+ 4* Most likely)/6 = [4+6+(4*5)]/6= 5 Months . 5 months * total cost (1400+1600+2000) = 25000 is the actual cost. So, the savings will be 60000-25000= 35000.


NEW QUESTION # 382
專案經理被指派負責技術研究專案。專案團隊已經分配,主要主題專家 (SME) 向專案經理發送了執行專案所需的技術技能清單。
專案經理接下來該做什麼?

  • A. 與專案團隊會面,了解他們的技能並確定潛在的差距和培訓要求。
  • B. 將清單傳送給專案團隊並要求他們接受所需技能的訓練。
  • C. 與專案發起人討論該列表,以確認資源具有所需的技能。
  • D. 請職能經理審查資源庫並推薦合適的人員加入團隊。

Answer: A


NEW QUESTION # 383
在每日站立會議中,開發人員表示將不會交付積壓的項目,因為他們需要在接下來的幾天內意外休假。積壓項目是用戶在下一次沖刺評審中期望的功能的先決條件。
項目負責人應該做什麼?

  • A. 要求開發經理提供幾天的替代品。
  • B. 要求開發商推遲休假,直到積壓的項目交付為止。
  • C. 與產品負責人合作更改衝刺待辦事項中的優先級。
  • D. 與產品負責人合作,通知用戶該功能已延遲。

Answer: A


NEW QUESTION # 384
一段時間以來,人們對誰負責提供專案的關鍵利益提出了質疑。
專案經理接下來該做什麼?

  • A. 了解情況的背景並將問題上報給指導委員會。
  • B. 與客戶會面,與利益接收者達成共識,並確定提供利益的方式。
  • C. 在風險登記冊中記錄風險並產生風險應對措施及其各自的相關計劃。
  • D. 與相關利害關係人會面,明確定義他們在利益方面的角色和責任

Answer: D

Explanation:
Explanation
The project manager should meet with the stakeholders involved to clearly define their roles and responsibilities with regard to the benefit. This will help to clarify the expectations, avoid confusion, and ensure alignment of the project objectives with the business needs. Option A is not the best answer because documenting the risk in the risk register and generating the risk responses and their respective associated plans is a reactive approach that does not address the root cause of the problem. Option B is not the best answer because meeting with the customer to obtain consensus with the recipient of the benefit and determine a means to deliver the benefit may not resolve the issue of who is responsible for delivering the benefit. Option C is not the best answer because understanding the context of the situation and escalating the problem to the steering committee may not be necessary or appropriate if the project manager can resolve the issue by meeting with the stakeholders involved. References: Top 60+ PMP Exam Questions and Answers for 2023 - KnowledgeHut However, I cannot guarantee that this answer is 100% verified or accurate, as it is based on a third-party source and not the official PMI reference materials. Therefore, I suggest you to consult the official PMI website2 or other reliable sources for more information and confirmation. I hope this helps.


NEW QUESTION # 385
項目經理必須安排額外的規劃會議來添加國際利益相關者的要求。利益相關者對產品不能滿足客戶需求表示擔憂。
項目經理在開發產品時應該考慮哪些因素?

  • A. 責任矩陣
  • B. 資源的可用性
  • C. 利益相關者的位置
  • D. 利益相關者的需求

Answer: D


NEW QUESTION # 386
在專案啟動會議上,客戶表示該專案的效益將成為公司最重要的收入來源。客戶需要盡快找到為公司創造價值的機會。
專案經理該做什麼?

  • A. 規劃專案迭代時考慮價值交付。
  • B. 制定專案管理計劃以更快地實現專案目標。
  • C. 使專案目標與公司的收入目標一致。
  • D. 應用專案進度壓縮技術來更快地交付效益。

Answer: A


NEW QUESTION # 387
在收尾過程中,項目經理了解到一項可交付成果未滿足客戶的期望。項目經理應該如何進行?

  • A. 與客戶會面,就雙方都滿意的交付範圍達成一致。
  • B. 要求客戶發出變更請求,並提供信息進行分析並提供解決方案。
  • C. 聯繫項目發起人並尋求幫助以與客戶協商項目結束。
  • D. 審查可交付成果要求,檢查客戶批准標準,然後進行相應處理。

Answer: D


NEW QUESTION # 388
專案經理意識到團隊成員是混合方法的新手,並且不重視站立會議。團隊成員經常遲到、偏離解決方案或乾脆跳過會議。
專案經理應該如何與專案組改善這種情況?

  • A. 讓專案團隊參與實施和改善站立會議的關鍵面向。
  • B. 在站立會議中加入每日腦力激盪會議,以解決懸而未決的問題。
  • C. 請產品負責人刪除不遵守站立會議規則的團隊成員。
  • D. 向所有團隊成員發送每日回顧報告,而不是召開站立會議。

Answer: A

Explanation:
Explanation
Standup meetings are brief daily meetings that help teams catch up on the progress and challenges of their projects. They are a common practice in agile project management, but they can also be used in hybrid approaches that combine agile and traditional methods. The purpose of standup meetings is to share information, align on goals, and identify any blockers or risks that need to be addressed. Standup meetings are not meant to be long or detailed discussions, but rather quick and focused updates.
To improve the situation with the project team, the project manager should engage the team members in implementing and improving key aspects of the standup meetings, such as:
Setting clear expectations and rules for the standup meetings, such as the time, duration, location, format, and agenda.
Explaining the benefits and value of standup meetings for the team and the project, such as improved communication, collaboration, transparency, and accountability.
Encouraging active participation and feedback from all team members, and ensuring that everyone has a chance to speak and be heard.
Keeping the standup meetings brief, on track, and effective, by avoiding digressions, interruptions, or distractions, and by addressing any issues or questions offline or in separate meetings.
Making the standup meetings fun and engaging, by using different formats, tools, or techniques, such as gamification, visual aids, or online platforms.
By engaging the team in implementing and improving the standup meetings, the project manager can help the team members understand and value the standup meetings, and foster a positive and productive team culture.
References:
Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Seventh Edition. Project Management Institute.
Project Management Institute. (2020). Agile Practice Guide. Project Management Institute.
What Is a Daily Standup? | Coursera
Stand-up and deliver - Project Management Institute
Leading Virtual Stand Up Meetings - Project Management Academy


NEW QUESTION # 389
為產品提供開發支援的專案經理注意到,他們的一些長期客戶由於其產品交付的價值提高而轉向競爭對手。專案經理首先該做什麼?

  • A. 暫停正在進行的產品開發並與團隊討論。
  • B. 強化產品重點,重新奪回流失的顧客。
  • C. 詢問產品負責人產品的價值交付是否改變了。
  • D. 根據新的市場洞察請求對產品進行更改。

Answer: C


NEW QUESTION # 390
......

Verified PMP-CN dumps Q&As Latest PMP-CN Download: https://testking.realvce.com/PMP-CN-VCE-file.html